expand parking lot lighting
asheville nc
Department of Veterans Affairs
in process
DSS was contracted to expand and replace the Charles George VA Medical Center parking lot lighting and all relevant rewiring. This work included locating and marking all underground utilities, protecting utilities during construction, demo, installation of new poles, new concrete bases, LED streetlights, security cameras, rewiring of all streetlights on campus per contract drawings, and providing any erosion and sediment control needed during installation and repairing any surfaces or utilities to that are damaged during construction back to existing conditions or better. Phasing will be necessary to control and mitigate building and parking lot interruptions and downtimes. All work is to be performed outside of normal business hours.